Free Schedule of Values Template with Pay App Math

This free schedule of values template lists each part of the job with its scheduled value, then tracks work completed, materials stored, percent complete, retainage and the current payment due on each pay application. Print it as a G702/G703-style application and continuation sheet of our own design, or export it as CSV. It saves in your browser.

What Is a Schedule of Values?

A schedule of values is a list that breaks the contract sum into parts of the work, such as demolition, framing or electrical, each with a dollar value. The values add up to the contract sum, and each pay application bills the share of each line completed so far.

Owners, lenders and architects use it to check that what you bill matches the work in place. You use it to get paid on time for what you have done, and to show the balance left to finish.

How to Use the Schedule of Values Template

  1. Enter the project and contract details: the original contract sum, the net change from approved change orders, and the retainage percentages in your contract.
  2. Add one line per part of the work with its scheduled value. The template warns you until the lines add up to the contract sum to date.
  3. Each period, enter the work completed this period and any materials stored on site but not yet installed.
  4. Enter the total previously certified or paid. The summary shows the current payment due.
  5. Print or save a PDF for the owner, or export CSV for your accounting. “Start next period” rolls this period into the previous column for the next application.

Try “Load example” in the template to see a filled-in application before you enter your own job.

Pay Application Math, With a Worked Example

Add work completed and materials stored to get the total earned to date, subtract retainage, then subtract what was already certified. What is left is the current payment due.

The template’s example job has a $100,000 contract and a $5,000 approved change order, with 10% retainage on both work and stored materials. To date, $44,500 of work is complete ($18,500 on earlier applications and $26,000 this period) and $15,000 of materials is stored on site.

LineCalculationAmount
Contract sum to date$100,000 + $5,000$105,000.00
Total completed and stored to date$44,500 + $15,000$59,500.00
Retainage10% × $44,500 + 10% × $15,000$5,950.00
Total earned less retainage$59,500 − $5,950$53,550.00
Less previous certificates$18,500 − 10% retainage$16,650.00
Current payment due$53,550 − $16,650$36,900.00
Balance to finish, including retainage$105,000 − $53,550$51,450.00

Each line’s percent complete is completed and stored to date divided by its scheduled value, and its balance to finish is the scheduled value minus that amount.

Retainage, Overbilling and Common Mistakes

Most pay application problems come from three things: lines that do not add up to the contract sum, lines billed past 100%, and retainage rates that do not match the contract. The template checks all three before you print.

Retainage percentages and when retainage is released are set by your contract and, for many projects, by state prompt payment or retainage laws. Federal construction contracts follow the payment clause in FAR 52.232-5. This template is not legal advice.

When the scope changes, update the contract sum with an approved change order rather than stretching an existing line. Our guide to progress billing explains how to set up the schedule at the start of a job, and how to write an estimate covers building the line items it starts from. To bill the current payment due, add it to an invoice in the GuestMargin invoice maker. The late fee calculator helps if a pay application goes overdue.

Frequently Asked Questions

What is a schedule of values in construction?

It is a breakdown of the contract sum into parts of the work, each with a dollar value. The total equals the contract sum, and progress payments are billed against each line as the work is completed.

How is retainage calculated on a pay application?

Multiply the work completed to date by the retainage rate for work, and the stored materials by the rate for stored materials, then add them. Rates and release terms come from your contract and depend on your state.

What does materials presently stored mean?

It is the value of materials delivered and stored for the job but not yet installed. It is billed separately from work completed. When the materials are installed, move that value into work completed for the period.

Is this an AIA G702 or G703 form?

No. It follows the same widely used application-and-continuation-sheet logic, in our own layout and wording. If your contract requires official AIA documents, get them from AIA Contract Documents.

What if my lines do not add up to the contract sum?

The template shows the difference and blocks the final printout until you fix it. You can still print a version marked “Draft” for review. Usually the cause is a missed line or a change order not yet added.