Change Order in Construction: How to Write, Price and Get One Signed

By GuestMargin Editorial Team · Updated

For educational purposes. How we review →

Part of our Contractor Guides

Change Order in Construction: How to Write, Price and Get One Signed

A change order is a written, signed amendment to a construction contract that changes the scope of work, the price, the schedule, or all three. It names the change, the reason, the cost breakdown, the time impact and the new contract total, and both sides sign it before the extra work starts.

Unsigned verbal changes are an easy way to end up doing free work. “While you’re here, can you also…” turns into a dispute at the final invoice, because nobody wrote down what was agreed or what it cost. One rule fixes most of it: no signature, no start. For a genuine emergency, send a written confirmation the same day.

A change order only works if the original scope was clear, so it builds on the full estimating guide. This article covers when you need a change order, what to put on it, how to price it (including the time impact, not just materials) and what to do when a client won’t sign. It is general information, not legal advice: check your contract and state law.

What is a construction change order?

A construction change order is a signed agreement between the owner and the contractor (and the architect, on designed projects) that modifies the original contract. It can add work, remove work, change materials or methods, adjust the contract sum and extend or shorten the contract time. Once signed, it becomes part of the contract.

The original agreement is usually the estimate or quote the client signed. If you are not sure which document you sent, read the difference between an estimate, a quote and a bid, because it affects how much price movement the client already agreed to.

On AIA-based contracts, the American Institute of Architects describes a change order as a written agreement among owner, contractor and architect that changes the work, the contract sum, the contract time or a combination, and it becomes binding once all three sign (AIA Contract Documents).

When do you need a change order?

You need a change order any time the work, price or schedule will differ from what the signed contract describes. The usual triggers are owner-requested scope changes, unforeseen site conditions, design changes, code-required changes and allowance overruns. If you would want it in writing in a dispute, write the change order.

  • Owner-requested changes: an added outlet, a different tile, moving a wall.
  • Unforeseen conditions: rot under the subfloor, undersized framing, buried debris, wiring that isn’t to code.
  • Design changes: revised drawings from the architect or engineer.
  • Code or inspector requirements: work the inspector requires that wasn’t in the scope.
  • Allowance overruns: the client picks fixtures that cost more than the allowance in the contract.
  • Deductive changes: the client removes work, so the price goes down.

Some states require it. In California, for example, the home improvement contract law says a change order becomes part of the contract only if it is in writing and signed by the parties before the covered work begins, and it must state the scope, the amount added or subtracted, and the effect on progress payments or the completion date (Cal. Bus. & Prof. Code 7159). Other states have different rules, so check yours.

How to write a change order: what to include

To write a change order, start from the signed contract and fill in every field below. A complete change order identifies the original contract, describes the change and why it is needed, breaks down the cost, states the schedule impact, shows the original total, the change amount and the new total, and has dated signatures from both parties. Missing any one of these is where disputes start.

ItemWhat to writeWhy it matters
Change order number and dateCO-01, CO-02 in sequenceKeeps your change order log in order
Contract referenceOriginal estimate or contract number and date, job addressTies the change to the signed agreement
Description of the changeExactly what is added, removed or substituted, with quantitiesDefines the scope change and prevents “I thought that was included”
ReasonOwner request, unforeseen condition, design or code changeShows who caused the change
Cost breakdownLabor, materials, equipment, subs, markupLets the client see the price is fair
Schedule impactDays added or “no change”Protects you from delay claims
Original contract totalContract sum before this change (including prior change orders)Running total stays accurate
Change amountPlus or minusThe number being approved
New contract totalOriginal total plus or minus the changeWhat the final invoice will be based on
Payment termsWhen the change is billed (with the next progress payment, on completion, or a deposit)Avoids arguments about timing
Signatures and datesOwner and contractor (and architect, if applicable)Turns the request into an agreement

You can fill in each of these fields in the free estimate and invoice maker, which also produces change order documents without a signup. If you need the payment timing wording, see how to word your payment terms.

How does the change order process work?

The change order process runs in five steps: request, price, approve and sign, perform, then bill. Keep a change order log so every change has a number, a status and a signed copy, and so the final invoice reconciles with the contract plus every approved change.

The change order process in 5 steps: Request; Price; Approve and sign; Perform; Bill
The change order process in 5 steps. The process described in this guide.
  1. Request. The client asks for a change, or you find a condition that requires one. Write it down the same day, with photos. A change order request is not yet approval.
  2. Price. Work out labor, materials, markup and time impact (next section).
  3. Approve and sign. Get it signed before you start; a signed PDF beats a text message.
  4. Perform. Do the work as described. If it grows again, that is a new change order.
  5. Bill. Add the approved amount to the next invoice or pay application. The invoice should list the change order number, which is part of what a contractor invoice should include.

A simple log has six columns: number, date, description, amount, days, status (pending, approved, rejected, billed). You can keep it in the same app that sends your estimates; if you are shopping for one, look at software that sends estimates and gets you paid.

How do you price a change order?

Price a change order as direct cost (labor, materials, equipment, subs) plus markup for overhead and profit, plus time-related costs such as extra days of supervision or rentals. Your contract may set or cap the markup on change orders. When the scope is unknown, use time and materials with a not-to-exceed cap.

Price labor at your fully burdened rate per billable hour, not the wage. If you haven’t worked that out, start with how to calculate labor cost. Price the rest the same way you priced the original job; pricing a construction job step by step covers quantities, overhead and contingency.

Worked example (all costs illustrative). During a bathroom remodel with a $48,500 contract, demolition reveals rotted subfloor:

  • Labor: lead 10 hours x $53.60 = $536.00; helper 10 hours x $38.00 = $380.00. Labor total $916.00
  • Materials (plywood, lumber, fasteners): $420.00
  • Disposal: $85.00
  • Time-related costs (one extra day of dumpster rental and supervision): $150.00
  • Subtotal: $916.00 + $420.00 + $85.00 + $150.00 = $1,571.00
  • Markup at 15% (assumed; check your contract): $1,571.00 x 0.15 = $235.65
  • Change order amount: $1,571.00 + $235.65 = $1,806.65
  • New contract total: $48,500.00 + $1,806.65 = $50,306.65; contract time: plus 1 working day

Markup and margin are not the same. A 15% markup is a 13% margin ($235.65 / $1,806.65 = 0.130). If you plan your profit as a margin, see converting markup to margin before you set a change order rate.

Don’t forget the time impact. A change that adds a day can push every trade behind it, and that cost belongs in the price or the schedule line.

Change order vs construction change directive vs field order

A change order is an agreed change to scope, price or time, signed by both sides. A construction change directive orders the work to proceed before price or time is agreed. A field order, or minor change, adjusts the work without changing price or time. AIA publishes a standard form for each: G701, G714 and G710.

DocumentAIA formWho signsChanges price or time?When it is used
Change orderG701Owner, contractor, architectYes, as agreedAll parties agree on the change and its cost and time
Construction change directiveG714Owner and architectYes, adjustment set laterWork must move forward before cost or time is agreed
Minor change / field order (architect’s supplemental instructions)G710Architect aloneNoMinor changes or clarifications within the existing scope

AIA G701 is AIA’s standard change order form, signed by the owner, contractor and architect once all three agree on the change. The AIA A201 general conditions document is where the contract rules for changes in the work live: Article 7 governs them. If a contractor agrees with a change directive’s pricing, it becomes a change order; if not, A201 sets the procedure for interim and final adjustments. If a contractor believes a minor-change instruction affects cost or time, AIA’s guidance is to give notice before proceeding. AIA forms are licensed documents: buy and use the official ones when your contract calls for them.

How do change orders affect progress billing?

On jobs billed in stages, each approved change order is added as its own line on the schedule of values, and the contract sum to date grows by the change amount. The next pay application bills the change’s completed share like any other line. Unsigned changes should not appear on a pay application.

On a monthly pay application, the summary shows the original contract sum, the net change by change orders and the revised contract sum. A change order line that is half finished is billed at 50% of its value, less retainage if the contract has it. The full method, with a worked example, is in AIA-style G702/G703 pay applications. To set up the lines, start from the schedule of values template and add each change as CO-01, CO-02 and so on.

What if the client won’t sign the change order?

If the client won’t sign, don’t start the extra work unless your contract or the situation (safety, an emergency) requires it. Put your position in writing, offer options, and read your contract’s change and dispute clauses. Whether you can get paid for unsigned work depends on the contract and your state’s law.

  • Clarify the scope. Point to the line in the original estimate that does or doesn’t include the work.
  • Offer alternatives: a cheaper option, or time and materials with a not-to-exceed cap.
  • Document an emergency. If you must act to protect the property, send a dated written notice with photos and the estimated cost the same day.
  • Know your remedies. Lien rights, prompt payment rules and home improvement laws differ by state. Check with a construction attorney or your state contractor board.

Prevention is cheaper. Put a change order clause in every estimate: changes need a signed change order, use your stated rates and markup, and bill with the next payment. Back it up with clear deposit and late-fee terms. This is not legal advice.

Frequently Asked Questions

What is a change order in construction?

A change order in construction is a written amendment to the contract that changes the scope of work, the contract price, the schedule or a combination. Both the owner and the contractor sign it, plus the architect on designed projects. Once signed, it becomes part of the contract and adjusts the total the final invoice is based on.

Who pays for a change order?

Usually the owner pays for changes they request and, depending on the contract, for unforeseen site conditions. The contractor usually absorbs changes caused by its own errors or omissions. Who bears design errors also depends on the contract. The contract’s change and concealed-conditions clauses decide; read them before the job starts.

Can a contractor charge for extra work without a change order?

Sometimes, but it is risky. Depending on the contract and state law, a contractor may still recover for extra work the owner requested or accepted, but without a signed change order you carry the burden of proving it. Some states require signed written change orders on home improvement contracts. Check your contract and state law; this is not legal advice.

How much markup should go on a change order?

Use the markup your contract specifies; some contracts cap the percentage allowed for overhead and profit on changes. If the contract is silent, apply the same markup you used on the original estimate so the price is consistent and defensible. Add time-related costs separately. In our example, a 15% markup on $1,571.00 of cost added $235.65.

Does a change order have to be signed?

To be enforceable as a contract change, it should be signed by both parties, and some contracts and state laws require a signature before work starts. A signature is your best evidence that the client approved the scope and price. E-signatures generally work if your contract allows them. When in doubt, check your contract and state law.

The bottom line

Write every change down, price it at your real labor cost plus markup and time impact, and get a signature before you start. A clear original scope makes every change order easier, so revisit our step-by-step estimate guide if your estimates leave room for argument.