Part of our Contractor Guides

Progress billing is billing a share of the contract price as work is completed, usually once a month, measured line by line against a schedule of values. Each bill, called a pay application (a construction pay app), shows the work done to date, what was billed before, any retainage held back and the amount due now.
A pay application is only as good as the schedule of values (SOV) behind it. A front-loaded SOV, where early items are priced high to pull cash forward, can get flagged and slow payment. A balanced, line-by-line SOV that matches your estimate is what gets approved quickly.
That is why progress billing starts with how to write an estimate: the estimate’s line items become the SOV. Retainage, prompt payment and lien waiver rules vary by state and by contract. This is general information, not legal advice.
What is progress billing?
Progress billing is a payment method where the contractor bills for the portion of work completed in each period, usually monthly, rather than waiting until the job is finished. The amount comes from a percent-complete estimate for each line of the schedule of values, less retainage and less what was already billed.
It suits jobs longer than a billing cycle: additions, large remodels, build-outs and new homes. You get paid as you spend, and the client pays only for work in place. In construction, these progress payments are usually requested on a pay application rather than a plain invoice, and the contract sets the billing date, the review step and the payment deadline.
The document you start from matters. A fixed-price quote and a cost-plus estimate are billed differently, so check whether to call it a quote or an estimate before you set up billing.
Progress billing vs milestone billing vs deposits
Progress billing charges for the percentage of each line completed each period. Milestone billing charges fixed amounts when defined stages are reached. Deposit-plus-final billing collects an upfront payment and the balance at completion. The right method depends on job length, contract type and what your client or lender expects.
| Method | How the amount is set | Typical jobs | Paperwork needed |
|---|---|---|---|
| Progress billing | Percent complete of each SOV line, billed per period (often monthly), minus retainage | Commercial work, new homes, large remodels, lender-funded jobs | Schedule of values, pay application (G702/G703 or equivalent), often lien waivers |
| Milestone billing | Fixed amount or percentage due when a stage is complete (e.g., rough-in passed) | Mid-size remodels, roofing, kitchens | Payment schedule in the contract, invoice per milestone |
| Deposit and final | Upfront deposit, balance on completion | Short jobs: days to a few weeks | Deposit invoice, final invoice |
| Time and materials | Hours worked at stated rates plus materials and markup | Service work, repairs, undefined scope | Timesheets, receipts, periodic invoices |
Deposits still matter on progress-billed jobs; see invoicing a deposit or a final payment, and check whether your state caps residential deposits.
How do you build a schedule of values?
Build a schedule of values by breaking the contract sum into lines that match how you estimated and will build the job: by trade, phase or area. Each line gets a dollar value, and the lines must add up exactly to the contract sum. Value each line at its real cost plus a fair share of overhead and profit.

If you priced the job in a free construction estimate template, its line items are your first draft. Then:
- Use lines the owner can verify on site. “Framing” or “Electrical rough-in” can be inspected; “Phase 1” can’t.
- Split big lines by floor, area or labor and materials, so percent complete is easy to judge.
- Spread overhead and profit evenly. Front-loading (overvaluing early lines) can get an SOV rejected. Value each line at its cost plus your markup; see choosing a contractor markup.
- Add each approved change order as its own line (CO-01, CO-02) rather than editing the original values.
The quickest way to set up the lines is the schedule of values template. If you need to rebuild the numbers behind each line, how to price overhead and contingency into a bid walks through it.
What are AIA G702 and G703?
AIA G702 is the Application and Certificate for Payment: a one-page summary the contractor signs to request payment and the architect signs to certify the amount. AIA G703 is the Continuation Sheet: the line-by-line detail of the schedule of values. The contractor fills in G703 first and carries its totals onto G702.
These are licensed AIA documents. AIA’s instructions describe G703 as breaking the contract sum into portions of the work based on the contractor’s schedule of values, with totals carried to G702 (AIA G702 instructions; AIA G703 summary). The contractor signs G702, has it notarized and submits it with G703. If your contract requires AIA forms, buy the official ones from AIA Contract Documents; otherwise a pay application showing the same figures may be accepted, if your contract allows it.
What goes on the G703 continuation sheet
G703 has one row per schedule of values line and a column for each step of the math. In plain language (letters A to G as on the form; the last columns are described by what they hold):
| Column | What it shows (plain-language summary) | How to calculate it |
|---|---|---|
| A | Item number | Your SOV line number |
| B | Description of the work | The SOV line name |
| C | Scheduled value | Dollar value of the line |
| D | Work completed in previous applications | Column D + E from the last pay app |
| E | Work completed this period | Value of work installed since the last pay app |
| F | Materials presently stored (not yet installed) | Invoiced value of materials on site or in approved storage |
| G | Total completed and stored to date | D + E + F |
| Percent | Percent complete | G / C |
| Balance | Balance to finish | C – G |
| Retainage | Retainage, where the contract uses a variable rate by line | Retainage rate x the amounts it applies to |
What goes on the G702 summary
G702 takes the contract sum (adjusted by change orders) and the G703 totals through retainage and previous certificates for payment (everything certified on earlier pay apps) to the current payment due and the balance to finish; the worked example below follows the same order. If the architect certifies less than requested, AIA’s instructions say to initial each changed figure and attach an explanation.
How architect certification works
Architect certification is the review step on a construction pay app: the architect compares the contractor’s application with the work on site, then signs the certificate on G702 for the amount they agree is due. The owner pays the certified amount, not necessarily the amount requested. On jobs without an architect, the contract says who reviews the pay application instead.
How do you calculate a progress payment?
A progress payment equals the total completed and stored to date, minus retainage, minus everything certified in earlier pay applications. Put simply: (work this period + materials stored this period) x (1 – retainage rate), as long as nothing earlier was reduced. Calculate each line first, then total.
Illustrative example: a $120,000 addition with one approved $2,400 change order, 10% retainage (assumed; your contract sets it), pay application #3. Value labor lines at a burdened rate; see how to calculate labor cost.
| Line | C Scheduled | D Previous | E This period | F Stored | G Total | % (G/C) | Balance (C – G) |
|---|---|---|---|---|---|---|---|
| 1 Mobilization | $6,000 | $6,000 | $0 | $0 | $6,000 | 100% | $0 |
| 2 Demolition | $9,000 | $9,000 | $0 | $0 | $9,000 | 100% | $0 |
| 3 Framing | $24,000 | $14,400 | $9,600 | $0 | $24,000 | 100% | $0 |
| 4 Plumbing rough-in | $15,000 | $3,000 | $9,000 | $0 | $12,000 | 80% | $3,000 |
| 5 Electrical rough-in | $14,000 | $0 | $8,400 | $0 | $8,400 | 60% | $5,600 |
| 6 Drywall | $12,000 | $0 | $0 | $0 | $0 | 0% | $12,000 |
| 7 Cabinets and counters | $28,000 | $0 | $0 | $11,000 | $11,000 | 39.3% | $17,000 |
| 8 Finishes and punch list | $12,000 | $0 | $0 | $0 | $0 | 0% | $12,000 |
| 9 CO-01 Added window header | $2,400 | $0 | $2,400 | $0 | $2,400 | 100% | $0 |
| Totals | $122,400 | $32,400 | $29,400 | $11,000 | $72,800 | 59.5% | $49,600 |
Now the summary, step by step:
- Original contract sum: $120,000
- Net change by change orders: +$2,400
- Contract sum to date: $120,000 + $2,400 = $122,400
- Total completed and stored to date: $72,800
- Retainage at 10%: completed work ($32,400 + $29,400 = $61,800) x 10% = $6,180; stored materials $11,000 x 10% = $1,100; total $7,280
- Total earned less retainage: $72,800 – $7,280 = $65,520
- Less previous certificates for payment: $32,400 – 10% retainage = $29,160
- Current payment due: $65,520 – $29,160 = $36,360
- Balance to finish, including retainage: $122,400 – $65,520 = $56,880
Check it two ways. This period’s work plus stored materials is $29,400 + $11,000 = $40,400, and $40,400 x 0.90 = $36,360. The balance to finish is $49,600 of unbilled work plus $7,280 of retainage = $56,880. If either check fails, fix the math before you submit.
How does retainage work in progress billing?
Retainage is a percentage of each progress payment the owner holds back until the job is substantially complete or accepted, as security that the work will be finished and defects fixed. The rate, any cap, any reduction partway through the job and the release deadline are set by your contract and, in many states, by statute.
There is no single universal rate. Many states limit retainage on public projects, some also on private ones, and release deadlines differ. On federal construction contracts, the standard payments clause lets the contracting officer withhold up to 10% of a progress payment when satisfactory progress hasn’t been made, and requires release of the remainder once the work is substantially complete, keeping only what is needed to protect the government (FAR 52.232-5).
In the example above, retainage at 10% would reach $12,240 on the $122,400 contract sum at completion. Track retainage receivable separately and invoice its release as soon as the contract allows. On federal construction contracts, progress payments are generally due 14 days after the billing office receives a proper payment request (FAR 52.232-27, implementing the federal Prompt Payment Act). State prompt payment acts set their own deadlines. Check your state’s rules and your contract’s invoice payment terms.
Do lien waivers go with pay apps?
Often, yes. Many owners, lenders and general contractors require a lien waiver with each pay application: a conditional waiver for the payment being requested, and an unconditional waiver for the previous payment once it has cleared. Some states require specific statutory waiver forms, and a waiver in the wrong form may not be enforceable.
- Conditional waiver: releases lien rights for the amount only once payment is received.
- Unconditional waiver: releases them immediately; sign only after the money clears.
- Progress vs final: progress waivers cover work through a date; final waivers cover the job.
California publishes the conditional and unconditional progress and final waiver forms (California CSLB), and Texas makes a waiver unenforceable unless it substantially complies with the forms in Texas Property Code Section 53.284. Other states differ. Ask a construction attorney if unsure; this is not legal advice.
Why does a construction pay app get rejected or paid late?
Pay apps get rejected or paid late for avoidable reasons: math that doesn’t tie out, a front-loaded schedule of values, percent-complete claims the site doesn’t support, missing lien waivers, unsigned change orders billed as approved, and stored materials without proof of purchase, insurance or location.
- Math errors. Run the two checks from the example on every pay app.
- Overbilling or front-loading. Claiming 80% when the site looks like 60%, or inflated early lines, invites a review of every line.
- Missing waivers. Yours and, on larger jobs, your subs’ and suppliers’.
- Unapproved changes. Bill only signed changes; follow the change order process so each one has a number and a signature.
- Stored materials without backup. Attach invoices and photos, and confirm the contract allows billing for stored materials.
- Late submission. Miss the contract’s monthly pay app date and you may wait a cycle.
Can small contractors use progress billing?
Yes. Any job long enough to span more than one payment cycle can use progress billing. On a residential remodel, a simple monthly progress invoice that lists each line, its percent complete, prior billings and the amount due works without AIA forms, as long as the contract describes the billing method.
Write the method into the contract: billing date, how percent complete is measured, retainage (if any) and due date. Then send a progress invoice each period with the same columns as the example above. You can make the document free in your browser; built-in progress billing is planned for GuestMargin Pro (coming soon). Prefer a full app? Compare contractor invoicing software on progress invoicing.
Frequently Asked Questions
What is AIA billing?
AIA billing is progress billing done on the American Institute of Architects’ standard forms: the G702 Application and Certificate for Payment and the G703 Continuation Sheet. The contractor lists each schedule of values line with work completed and stored, applies retainage, subtracts previous payments and requests the balance. The architect reviews and certifies the amount before the owner pays.
What is the difference between G702 and G703?
G703 is the detail; G702 is the summary. G703, the continuation sheet, lists every schedule of values line with scheduled value, previous work, work this period, stored materials, percent complete and balance to finish. G702 carries those totals into a one-page summary with change orders, retainage, previous certificates and the current payment due, and holds the signatures.
How is retainage calculated on a pay application?
Multiply the retainage rate by the total completed and stored to date, often split between completed work and stored materials. In our illustrative example, 10% of $61,800 in completed work is $6,180 and 10% of $11,000 in stored materials is $1,100, so total retainage is $7,280. Your contract and state law set the rate and any reduction.
Can a small contractor use progress billing?
Yes. Small contractors can bill monthly or at set stages on any job that runs longer than a payment cycle. A clear schedule of values and a progress invoice showing percent complete, prior billings and the amount due are enough unless the contract requires AIA forms. State the billing method in the contract before work starts.
Do I need AIA software to bill AIA-style?
No. You need the official AIA forms only when your contract requires them, and they are sold by AIA Contract Documents. Otherwise, any pay application or progress invoice with the same figures works: scheduled values, work to date, stored materials, retainage, previous payments and current amount due. A spreadsheet or invoicing app can produce it.
The bottom line
Progress billing gets you paid as you build, but only if the schedule of values is balanced, the math ties out and the paperwork is complete. Build the SOV from your estimate, bill only signed changes, run the two checks on every pay app and track retainage separately.